Wallingford High Street shuts overnight from 10pm on 16 November and the A34 south of Milton closes every night to 20 November. Every other closure nearby is listed.
High Street in Wallingford closes overnight from 10pm on Monday 16 November, and the A34 southbound between Milton and Chilton shuts every night from Monday to Thursday this week. The Wallingford closure is at the St Martins Street and Castle Street junction, so a Thames Water engineer can get into the sewer basin. Oxfordshire County Council said in its notice that it intends to make the order (ref 600).
The A34 closure runs 9pm to 6am on the nights of 16, 17, 18 and 19 November, for improvement works. That is from National Highways’ seven-day closure report, edition of 13 November. Didcot drivers heading for Newbury and the south use that stretch.
West Street in Henley was due to reopen at the end of its closure today, Sunday 15 November. No new Henley town-centre closure has been published.
The next fortnight:
- South Stoke railway bridges: Cross Keys Road and then Ferry Road close overnight at the railway bridges, 9pm to 5am on the nights of 17 to 18 and 18 to 19 November, for bridge inspections (council intends to make, refs 598 and 599).
- Common Lane at Binfield Heath stays shut until Thursday 19 November for telecoms duct work (ref 595), with the diversion via Harpsden Road and Sonning Common Road.
- M4 junction 8/9 at Maidenhead, where the A404(M) meets the M4: part of the roundabout closes 9pm to 6am on the nights of Monday 16 to Thursday 19 November, with lane closures on the A404(M) and A308(M), for surveys.
- A34 at Peartree and Marcham: the A34 is closed between the Peartree slip roads, both ways, 9pm to 6am from Monday 16 to Thursday 19 November (northbound only on Wednesday). The Marcham slips shut northbound on Tuesday night and southbound on Thursday night.
- Trains: from Tuesday 17 to Thursday 19 November the 0018 Henley-on-Thames to Reading finishes at Twyford, with a connection on to Reading. On Sunday 22 November only two of the four tracks between Paddington and Reading are open, so trains run to an amended timetable. On the weekend of 28 and 29 November no trains run to or from Paddington at all, though GWR says Twyford to Henley trains still run (GWR planned engineering).
- On the river: Marsh Lock, just upstream of Henley, closes from Monday 23 November to 18 December for gate re-sheeting. Hambleden Lock, below Henley, closes from 30 November to 17 December. Benson Lock, above Wallingford, has been shut since 9 November and stays shut until 21 December. On Sunday 29 November the Cleeve reach, from Moulsford Railway Bridge to Wallingford, closes from 10am to 12pm and 1.30pm to 3.30pm for the Wallingford Winter Head rowing race (Environment Agency closure notice).
Two authorities decide how you get around Henley-on-Thames and neither of them tells you about the other. Oxfordshire County Council owns the roads, the roadworks and the buses. South Oxfordshire District Council owns the car parks. Neither publishes a list of what is shut right now.
The county’s live map shows every registered closure, utility dig and diversion as it happens: one.network for Oxfordshire. Everything below is what the map does not give you: the dated orders, the ones that are still only proposals, and the context.
Last checked 15 November 2026. The only new Oxfordshire traffic notice for this district since 6 November is a Thame closure in January, published on 11 November. National Highways’ figures are from its seven-day closure report for 13 to 19 November. We could not read the one.network map itself today, so anything registered there but not yet published as a notice is not in this list.
What is shut, and what is coming
Every entry here comes from a statutory traffic order published by Oxfordshire County Council or National Highways. The status column matters. An order that has been made is a decision. An order the council intends to make is a plan, and plans move.
| Where | What | When | Status |
|---|---|---|---|
| A4074, Oxford to Caversham | New 40mph and 50mph limits replacing the national speed limit on most of the corridor | In force since 24 July 2026 | Order made 20 July |
| Goring-on-Thames, Battle Road | Closed 24 hours between Cedarwood House and Cedar Wood Cottage for gas main replacement | 24 August to 11 December 2026 | Order made 17 August (T18397/AC) |
| A4130 Perimeter Road, Didcot | 50mph cut to 30mph for 1,370 metres, Avon Way roundabout to Hawksworth | From 24 August 2026, anticipated to 31 January 2028 | Order made 17 August (ref 257) |
| A415 Clifton Hampden and Culham | 60mph cut to 40mph, and to 20mph through Clifton Hampden, for construction access to Thame Lane | 31 August 2026 to 31 August 2027 | Order made 17 August (ref 252) |
| A418 Thame | 60mph cut to 40mph from the Oxford Road roundabout to the Buckinghamshire border, for a Bloor Homes construction access; the new order revokes the temporary 30mph order | To 24 April 2028 | Order made 24 August (TTRO 12), published 14 October |
| Six Didcot streets | School Streets: no motor vehicles at drop-off and pick-up, ANPR enforced | From 2 September 2026, term time only | Experimental order made 17 August |
| Shepherds Pit Lane, Stanton St John | Motor vehicles banned for its full length under the county Quiet Lanes programme; walking, cycling and horse riding unaffected | From 21 September 2026, up to 18 months | Experimental order made 7 September (CM/12.6.320/E0013) |
| Old Road, Wheatley | Closed for its full extent for water mains replacement | 28 September to 21 December 2026 | Order made 14 September (ref 288) |
| Cuddesdon High Street | Closed from the High Street junction to Mill House for water mains replacement | 28 September to 14 December 2026 | Order made 14 September (ref 228) |
| Goring-on-Thames, Cleeve Road | Closed 24 hours from the Mill Road junction to outside No.21, gas main replacement in three phases | 29 September 2026 to 12 February 2027 | Order dated 7 September (T18438/AC) |
| A34, Milton to Chilton | Order allows a full weekend closure for resurfacing; the southbound overnight closures from 2 to 6 October have finished, and separate southbound night closures for improvement works are booked 16 to 19 November | The reserve weekend from 23 October passed with no closure booked. National Highways' report for 13 to 19 November books no weekend closure | Order varied, in force 27 September (NH/SE/2026/A34/74) |
| M4 junction 8/9, Maidenhead | Partial roundabout closure, with lane closures on the A404(M) and A308(M), for surveys | 9pm to 6am nightly, 16 to 19 November 2026 | National Highways seven-day closure report, 13 to 19 November |
| A34 southbound, Milton to Chilton | Carriageway closed overnight for improvement works | 9pm to 6am, nights of 16, 17, 18 and 19 November 2026 | National Highways seven-day closure report, 13 to 19 November |
| A34 at Peartree | Carriageway closed between the exit and entry slip roads for resurfacing, both ways (northbound only on 18 November) | 9pm to 6am, nights of 16 to 19 November 2026 | National Highways seven-day closure report, 13 to 19 November |
| Stoke Talmage Road, Wheatfield and Tetsworth | Closed from the A40 to the Stoke Talmage access road for new drainage | 9 November to 4 December 2026 | Council intends to make (ref 403) |
| Common Lane, Binfield Heath | Closed for telecoms duct installation; access for homes and emergency services where possible; diversion via Harpsden Road, Sonning Common Road and Common Lane | 11 to 19 November 2026 | Order notice published 6 November (ref 595) |
| Mill Road, North Weston, Thame | Closed for parapet and verge repairs | 5 November 2026 to 22 January 2027 | Order made 26 October (ref 440); diversion via Crendon Road, Sandy Lane, the Western Bypass and Thame Road |
| High Street, Wallingford | Closed overnight at the St Martins Street and Castle Street junction so a Thames Water engineer can enter the sewer basin | From 10pm, 16 November 2026 | Council intends to make (ref 600) |
| South Stoke, Cross Keys Road then Ferry Road | Closed overnight at the railway bridges for bridge inspections | 9pm to 5am, 17 to 18 and 18 to 19 November 2026 | Council intends to make (refs 598, 599) |
| Chinnor Road, Towersey | Closed outside No.2 for a water apparatus installation | 25 to 28 November 2026 | Council intends to make (ref 676) |
| Sydenham Road, Sydenham | Closed outside the White House for a new water connection | 24 to 28 November 2026 | Council intends to make (ref 704) |
| Whites Orchard, Blewbury | Closed from Bessels Way for a water pressure monitoring point | 30 November to 2 December 2026 | Council intends to make (ref 690) |
| A4155 Reading Road, Shiplake | 30mph limit to be extended 44 metres north; the objection period closed on 23 October and no decision has been published | Proposal only | Proposed order (CM/12.6.341/P0140) |
| A34 southbound lay-bys, Peartree to Marcham | All lay-bys beside the southbound carriageway closed around the clock, in phases, for carriageway repairs | About six weeks from 2 November 2026 | National Highways intends to make (NH/SE/2026/A34/85) |
| Baldon Lane, Marsh Baldon | Closed for a JN Bentley rising main replacement; diversion via the B480, Grenoble Road and the A4074 | 8am 9 November 2026 to 5pm 29 January 2027 | Council intends to make (ref 468) |
| Weston Road, Lewknor | Closed outside No.3 to install flushing valves, M Group Water | 7 to 12 December 2026 | Council intends to make (ref 777) |
| Shiplake Bottom, Peppard Common | Closed to lay about 60m of fibre duct for Openreach; diversion via Gallowstree Road, Stoke Row Road and Gravel Hill | 14 to 18 December 2026 | Council intends to make (ref 741) |
| Goring-on-Thames, High Street | Closed from Wallingford Road to Thames Road for gas main replacement; diversion via Moulsford and Wallingford | 4 January to 2 April 2027 | Council intends to make (ref 582) |
| Oxford Way, Chalgrove | Closed by The Brook Surgery land for a Network Plus connection to High Street; diversion via the B480, Monument Road and High Street | 4 to 8 January 2027 | Council intends to make (ref 910) |
| Windmill Road, Thame | Closed from the Corbetts Way junction to the Phoenix Trail cycle track for a waste water connection by STD Civils; working hours 9am to 3pm; no through road, so no diversion | 11 to 22 January 2027 | Council intends to make (ref 1188), notice published 11 November |
| Castle Street, Wallingford | Closed outside No.1 to repair a collapsed sewer pipe the notice links to possible flooding; diversion via Castle Road, Shillingford Road, the A4074, The Street and High Street | 11 January to 1 February 2027 | Council intends to make (ref 854) |
| Collett, Didcot | Southern arm of the roundabout closed to build the new HIF1 road layout | 17 February 2027 to 17 February 2028 | Council intends to make (ref 522) |
Five entries have come off the table since our check on 9 November, all past their end dates: West Street in Henley, Hurdlers Green in Watlington, the Nuns Acre footpath in Goring, the A34 northbound night closures between Marcham and Abingdon, and the A404 and M40 junction 4 closures at Handy Cross. Three are new: Windmill Road in Thame in January, and two sets of A34 night closures this week.
One Henley footpath change is permanent rather than temporary. On 29 September South Oxfordshire District Council confirmed an order stopping up parts of Henley-on-Thames Footpaths 6 and 8, and about 59 metres of an unrecorded path, beside 78 Deanfield Road. The order exists to let a residential annex be built there under planning permission P24/S3241/FUL. It comes into force when the county council certifies it. Anyone challenging its validity has six weeks from first publication to apply to the High Court.
One order made on 28 September looks bigger than it is. Since 5 October the county has moved every one-way street, no-entry, bus lane and turning ban in South Oxfordshire into a new “map-based” order. The council says this is administrative only and changes nothing on the road. Parking restrictions are not affected.
Some of these are worth more than a table row.
Wallingford High Street and South Stoke this week
No street in Henley town has a dated closure in the next fortnight. West Street, shut from the Hop Gardens junction to No.132 from 13 to 15 November for Thames Water work (ref 519), was due to reopen at the end of today, Sunday 15 November.
In Wallingford, the county council intends to close High Street overnight from 10pm on Monday 16 November, at the St Martins Street and Castle Street junction, so a Thames Water engineer can enter the sewer basin (ref 600).
At South Stoke, near Goring, Cross Keys Road and then Ferry Road close at the railway bridges from 9pm to 5am on the nights of 17 to 18 and 18 to 19 November, for bridge inspections (refs 598 and 599). Both are intentions, not yet made orders.
Towards Reading, Common Lane at Binfield Heath stays shut until 19 November for telecoms duct work (ref 595), with the diversion via Harpsden Road and Sonning Common Road.
Goring is losing roads to gas main replacement until April
SGN’s gas main replacement in Goring-on-Thames is the longest running set of closures in this district, and it is being ordered in pieces rather than announced as one scheme.
- Battle Road has been shut around the clock since 24 August, between Cedarwood House and Cedar Wood Cottage. The order runs to 11 December 2026. The signed diversion is Battle Road, Elvendon Road, Wallingford Road, Reading Road, the B4526, Goring Road and Elvendon Lane.
- Cleeve Road closes around the clock from 29 September, from the Mill Road junction to outside No.21, in three phases. That order was dated 7 September and runs to 12 February 2027. The diversion is Mill Road, Wallingford Road and the High Street.
- The footpath beside 11 Nuns Acre was due to be closed from 12 October to 13 November, and that order has now run its course.
- High Street is next. The council said in a notice published on 17 September that it intends to close it from the Wallingford Road junction to the Thames Road junction from 4 January to 2 April 2027, for gas mains replacement by I&G Contractors. The signed diversion would be a long loop: Wallingford Road, Port Way, Nosworthy Way, Reading Road and back through Moulsford. This is an intention, not yet a made order.
Access stays open for emergency services, for the works, and for homes that can only be reached from the closed sections. Cyclists and pedestrians keep Cleeve Road.
The motorway and A34 nights this week
Henley’s nearest motorway junction is the M4 at junction 8/9, reached by the A404(M). National Highways’ seven-day closure report for 13 to 19 November books surveys there again on four nights this week:
| Night | What is closed | Times |
|---|---|---|
| Sunday 15 November | A404(M) northbound junction 9b exit slip | 9pm to 6am |
| Monday 16 to Thursday 19 November | M4 junction 8/9 roundabout, partly closed, with lane closures on the A404(M) and A308(M), for surveys | 9pm to 6am |
The A34 is busier:
| Night | What is closed | Times |
|---|---|---|
| Monday 16 to Thursday 19 November | A34 southbound, Milton to Chilton, for improvement works | 9pm to 6am |
| Monday 16 to Thursday 19 November | A34 at Peartree, between the exit and entry slips, for resurfacing: northbound every night, southbound on 16, 17 and 19 November | 9pm to 6am |
| Monday 16 November | A34 northbound Milton exit and entry slips | 9pm to 6am |
| Tuesday 17 November | A34 northbound Marcham exit and entry slips | 9pm to 6am |
| Wednesday 18 November | A34 southbound, Botley to Hinksey Hill | 9pm to 6am |
| Thursday 19 November | A34 southbound Marcham exit and entry slips | 9pm to 6am |
National Highways’ varied order for Milton to Chilton still allows a full weekend closure for resurfacing. Its reserve weekend from 23 October passed with no closure booked, and the current report books no weekend closure there, only the weeknight southbound closures above. Check the report before you travel, because it is re-issued daily and plans change.
National Highways has also said it intends to close every lay-by on the southbound A34 between Peartree and Marcham, in phases, for about six weeks from 2 November, for carriageway repairs.
The A4074 is a slower road than it was
The main route from this side of the district to Oxford changed on 24 July 2026. Oxfordshire County Council made orders on 20 July replacing the 60mph national speed limit with 50mph along most of the A4074 between Nuneham Courtenay and Woodcote, and dropping the Benson to Crowmarsh section and the Cane End to Caversham section to 40mph. The A4130 Wallingford bypass went to 50mph at the same time.
More than half of the 564 people who responded to the consultation objected to every single section of it. The council approved the scheme anyway. The full list of what changed, who objected and what the council said back is in our report: the A4074 speed limits are now in force.
Six Didcot streets close at school run times
Oxfordshire County Council made experimental orders on 17 August introducing School Streets at Willowcroft Community Primary School and St Birinus Boys School in Didcot. Since Wednesday 2 September motor vehicles have been banned at the following points between 8am and 9am and between 2.30pm and 3.30pm, Monday to Friday in term time only:
- Abbott Road, at its eastern and western junctions with Queensway
- Glebe Road, northern end, at its junction with Newlands Avenue
- Lynmouth Road, at its junction with Newlands Avenue
- Mereland Road, northern end, at its junction with Kynaston Road
- Mereland Road, southern end, at its junction with Green Close
- Ridgeway Road, northern end, at its junction with Kynaston Road
Enforcement is by ANPR camera, active only during those hours, issuing penalty charge notices. Residents of the affected streets can register a vehicle for exemption. Emergency services, blue badge holders, taxis, carers, school buses, Royal Mail and waste and utility vehicles are also exempt.
The council had originally intended to start this trial earlier and says the delay was down to procuring the ANPR cameras. The experimental orders can run for a maximum of 18 months, and the point of an experimental order is that the council can be told during it whether it is working.
The summer resurfacing programme has finished
Oxfordshire’s planned road maintenance programme covers the end of May to early October 2026, and the council says it is resurfacing 33 sites and more than 85,000 square metres of road across the county in that window. Every South Oxfordshire date on it has now passed: Park Corner at Nettlebed, St Georges Road in Wallingford, Eastfield Lane at Whitchurch, Church Lane at Shiplake, Reading Road in Henley on 4 August and Gillotts Lane at Harpsden on 5 August. No new South Oxfordshire site has been added since.
What comes next in this district is not resurfacing but microsurfacing and surface dressing, and it is concentrated on Didcot, Chilton, Blewbury and Cholsey in the first half of October. That run is now over: the last of it, Rowland Close in Wallingford, was due to reopen at 4pm on 14 October. The county’s list of upcoming resurfacing schemes, checked on 14 October, has no South Oxfordshire road after Lower Icknield Way at Chinnor (29 September to 2 October). The council’s own caveat is worth repeating: “timings and locations may change to suit weather condition”.
The road build that will shape the next few years
The largest highway project in the district is not in Henley at all. Oxfordshire County Council is delivering four linked schemes around Didcot: the A4130 widening east of Milton Interchange, the Didcot Science Bridge over the A4130, the Great Western main line and Milton Road, the Didcot to Culham river crossing, and the Clifton Hampden bypass. Between them they add 19km of walking and cycling paths and 18 new bus stops, funded by Homes England grant, Enterprise Oxfordshire investment, developer contributions under section 106 and the council’s own capital budget.
On 3 August 2026 the county council named GRAHAM as the contractor for the river crossing: 3.6km of single carriageway from the A4130 at Collett roundabout to the A415 at Culham, with bridges over the Appleford railway sidings and over the Thames, and about two and a half years of construction ahead of it.
The order that spells out what that means arrived on 2 September. GRAHAM intends to close the southern arm of the Collett roundabout for a full year, from 17 February 2027 to 17 February 2028, to build the new HIF1 road layout, with traffic sent round via the A4130 and Hawksworth.
The rest is already visible in the traffic orders. The Thames Valley Path at Culham has been closed since 6 March 2026 for construction of the river crossing bridge, with the order running to 30 November 2027 and the council stating plainly that “there is no alternative nearby crossing”. The 30mph limit now imposed on 1,370 metres of the A4130 Perimeter Road at Didcot is anticipated to last until 31 January 2028.
For anyone driving between the Henley side of the district and the A34, that is several years of live construction across the routes you would use.
Parking: the three-hour problem
Henley is the odd one out among the district’s towns, and it is not close.
Kings Road (317 spaces) and Greys Road (133 spaces) are Henley’s two big car parks and both stop at three hours: one hour free with a ticket, £2.30 for two, £3.50 for three. Kings Road bars a return within two hours, Greys Road within one. Between them that is 450 spaces with no all-day option. The town’s only ten-hour council space is Southfields, which has 54 spaces at £5.30 for five hours and £6.30 for ten, with a monthly permit at £68, or £34 on the discounted rate. Southfields also sells a market trader permit at £164 a year or £14 a month for one day a week. All three tariffs were unchanged when we rechecked the council’s car park pages on 18 September.
Wallingford’s Cattlemarket and Thames Street, Thame’s Cattlemarket and Didcot’s Edinburgh Drive all sell the ten-hour ticket at £6.30. Didcot also runs an annual permit at £819, or £409 for a low-emission vehicle. In all of them the first hour is free but you still need to display a ticket, and every car park takes cash, card or the pay by phone app with a location code posted on the machine.
Two things to watch. The councils consulted on new Off-Street Parking Orders for South Oxfordshire and Vale of White Horse car parks between 9 April and 8 May 2026, so check the car parks pages before assuming these tariffs have survived. And in Thame, the Upper and Lower High Street car parks both close for the September Fair.
Four disabled bays in Henley are proposed for removal
Separately, the county council is consulting on removing four Disabled Persons Parking Places in Henley, at Crisp Road, Trust Corner and two on New Street, and on moving the Market Place bay eight doors along. Goring and Sonning Common lose bays too. Objections closed at 5pm on Friday 2 October 2026, and the county has not yet published a decision. The full list, town by town, is in our report: four Henley disabled parking bays face removal.
On the river: lock closures this autumn
If you take a boat out, three local locks close for engineering work before Christmas, and the first has already shut. The Environment Agency’s River Thames restrictions page, rechecked on 15 November, lists:
- Benson Lock, above Wallingford: closed to navigation since Monday 9 November, until 21 December 2026, for repairs to the lock chamber.
- Marsh Lock, just upstream of Henley: lock gate re-sheeting, 23 November to 18 December 2026.
- Hambleden Lock, below Henley: head and tail works to upgrade the hydraulics, 30 November to 17 December 2026. The earlier phase listed for 2 to 20 November is no longer on the page.
- Temple Lock, towards Marlow: lock gate re-sheeting, 11 January to 22 March 2027.
Restrictions and races on the local reaches:
- Marsh reach: restrictions under the arch of the Loddon Drive railway bridge for gas pipe repairs, until 27 November.
- Shiplake: a tree obstruction in the right-hand channel (looking upstream) at Phillimore Island, listed from 23 October until further notice, and an obstruction on the approach to the Shiplake Lock tail gates.
Marsh Lock itself was shut on 1 November by a public power fault and was back in full operation on 2 November, the agency says.
The drought restrictions between Goring and Culham locks, listed from 3 August, are no longer on the page.
Buses
The £2 single fare cap returns on 1 January 2027, the county council confirmed on 27 July 2026. Nine Oxfordshire operators took part in the original scheme from January 2023. The council has said it cannot cut MyBus fares before the cap starts, and will review that pricing when it does. Until January, single fares are whatever the operator charges.
One operator objection is worth knowing about, because it is about the road rather than the fare. Thames Travel, which runs the X40 along the A4074, objected strongly to the new speed limits on the grounds of journey time. The council’s own timed observation of an X40 run in each direction put the cost at about 79 seconds southbound and 57 seconds northbound, against the operator’s estimate of six to seven minutes, and officers approved the scheme on that basis.
What this means in practice
If you use Wallingford High Street at night, the council intends to close it at the St Martins Street and Castle Street junction from 10pm on Monday 16 November.
If you drive towards Reading through Binfield Heath, Common Lane is shut until 19 November. If you go to Thame from the Long Crendon side, Mill Road at North Weston is shut until 22 January.
If you use the A34 at night, the southbound side between Milton and Chilton is shut 9pm to 6am from Monday 16 to Thursday 19 November.
If you take the train, the last train of the night, the 0018 to Reading, ends at Twyford from 17 to 19 November. Sunday 22 November runs to an amended timetable between Paddington and Reading, and on 28 and 29 November no trains run to or from Paddington. Twyford to Henley trains still run that weekend.
If you live in or drive through Goring, assume the gas works are there until at least December on Battle Road and until February on Cleeve Road, with High Street due to follow from January to April.
If you are shopping in Henley, three hours is your ceiling in the main car parks, and £3.50 buys all of it. Nobody is going to sell you a fourth hour at Kings Road.
If you drive the A4074, the limits changed on 24 July and the signs are up. The council itself expects enforcement to be the deciding factor in whether anything improves, because two councillors and a parish council said as much during the consultation.
Frequently asked questions
Is Market Place in Henley closed?
Not under any current order. Oxfordshire County Council’s overnight closure of Market Place, from the Duke Street junction to outside 27-31, ran from 16 September with an anticipated finish of 6.30am on Saturday 17 October 2026, for a Network Plus connection. No extension or new order for Market Place appears in any notice published up to 28 October.
When is West Street in Henley closed?
West Street was closed from Friday 13 to Sunday 15 November 2026, from the Hop Gardens junction to outside No.132, for Thames Water work (ref 519), and was due to reopen at the end of that closure. No further West Street order has been published.
Where can I see current roadworks in Henley and South Oxfordshire?
On Oxfordshire County Council’s live map at one.network/custom/oxfordshire, which shows registered closures, utility works and diversions as they happen. Planned resurfacing with dates is listed separately on the council’s planned road maintenance page. Neither lists the statutory traffic orders, which is why the table above exists.
Is the B4445 Chinnor to Thame road open again?
The closure order ran from 21 September to 8 October 2026, between the Chinnor Road junction and the entrance to Waterlands Farm Bungalow. The county’s resurfacing list gives the work as finished on 5 October, and the road is in no newer order we have found. Check the one.network map before you set off.
Are the M4 junction 8/9 slip roads closed?
Partly, at night. National Highways’ seven-day closure report for 13 to 19 November books a partial closure of the junction 8/9 roundabout, with lane closures on the A404(M) and A308(M), 9pm to 6am on the nights of Monday 16 to Thursday 19 November, for surveys. The A404(M) northbound junction 9b exit slip shuts 9pm Sunday 15 November to 6am.
How long are the Goring gas works going on for?
Battle Road is closed until 11 December 2026 and Cleeve Road from 29 September 2026 to 12 February 2027, both around the clock, both for gas main replacement. A footpath at Nuns Acre was due to be closed until 13 November. The council also intends to close High Street, Wallingford Road to Thames Road, from 4 January to 2 April 2027.
What is the speed limit on the A4074 now?
Mostly 50mph between Nuneham Courtenay and Woodcote, replacing the 60mph national speed limit, with 40mph from Benson to Crowmarsh and from Cane End to Caversham. The A4130 Wallingford bypass is 50mph. The orders were made on 20 July 2026 and came into force on 24 July.
Is the A34 closed this week?
Not fully, but parts of it shut at night. National Highways’ report for 13 to 19 November lists the A34 southbound between Milton and Chilton closed 9pm to 6am on the nights of 16 to 19 November, the carriageway between the Peartree slips closed on the same nights, and slip closures at Milton on 16 November and Marcham on 17 and 19 November. The varied order for Milton to Chilton (NH/SE/2026/A34/74) still allows a full weekend closure; the report books none. Check the closure report before travelling.
How long can you park in Henley town centre?
Three hours in the two main council car parks. Kings Road and Greys Road both charge one hour free with a ticket, £2.30 for two hours and £3.50 for three, and sell nothing longer. Kings Road bars a return within two hours, Greys Road within one. Southfields is the only council car park in Henley with a ten-hour ticket, at £6.30, and it has 54 spaces.
How much is all-day parking in Wallingford, Thame or Didcot?
£6.30 for ten hours at Wallingford Cattlemarket and Thames Street, Thame Cattlemarket and Didcot Edinburgh Drive. A monthly permit is £68, or £34 at the discounted rate; Didcot also sells an annual permit at £819, or £409 for a low-emission vehicle.
What is being built at Didcot?
Four county council schemes: the A4130 widening, the Didcot Science Bridge, the Didcot to Culham river crossing and the Clifton Hampden bypass. GRAHAM was appointed in August 2026 to build the 3.6km river crossing, which includes bridges over the Appleford railway sidings and the Thames and will take about two and a half years. The southern arm of the Collett roundabout is due to close for a year from 17 February 2027.
When does the £2 bus fare cap come back?
1 January 2027, confirmed by Oxfordshire County Council in July 2026. Until then operators charge their own single fares.
Who do I report a pothole to?
Oxfordshire County Council, not the district council. The county is the highway authority for every road in South Oxfordshire except the trunk network.
Sources
- Oxfordshire County Council statutory traffic notices published on the Public Notice Portal on 23 July, 19 August, 26 August, 2 September and 4 September 2026, for every order, date, reference and status in the table, plus the Thames Water repair orders.
- Market Place and Fawley Bottom Lane closure notice, Oxfordshire County Council, published 11 September 2026 for the Market Place order of 7 September, reference 466, its 7pm to 6.30am hours, the diversion and the 17 October anticipated finish, and for the Middle Assendon pole replacement on 22 October.
- Oxfordshire County Council notices published 16 September 2026 for the made B4445 order of 14 September, the made Old Road and Cuddesdon orders, and the November closures at Cholsey, Brightwell Baldwin and Cuxham, Sydenham and Blewbury.
- Oxfordshire County Council notices published 9 September 2026 for the Mill Road closure at North Weston, the Wallingford High Street sewer works, the Towersey water connection and the South Stoke railway bridge inspections.
- Oxfordshire County Council traffic notices published 10 September 2026 for the Stanton St John Quiet Lanes experimental order of 7 September and its 21 September start.
- Goring-on-Thames gas main replacement: the Battle Road and Nuns Acre notice, 20 August 2026 and the Cleeve Road notice, 27 August 2026.
- National Highways amended notice for the A34 Milton to Chilton weekend closure, published 17 September 2026, reference NH/SE/2026/A34/74, for the varied order, the 27 September commencement, the approach speed restriction, the dates, the reserve weekend and the diversion. It supersedes the notice of intent of 3 September.
- Oxfordshire County Council notices published on the Public Notice Portal on 17 September (Goring High Street, Cleeve Road), 23 September (Blewbury, Honey Lane, Green Close), 24 September (Beech Lane, Woodcote), 25 September (the Shiplake 30mph proposal), and 30 September (Goldsmiths Lane, Cholsey, Marsh Baldon, Jubilee Way, Queens Road, Mowbray Road, Station Road, the Didcot and Chilton microsurfacing), the South Oxfordshire map-based order and the Thurningdown closure, 30 September, and Shiplake Bottom, 2 October 2026.
- National Highways seven-day road closure report, edition starting 1 October 2026, for the nightly A34 southbound closure times.
- South Oxfordshire and Vale of White Horse proposed Disabled Persons Parking Places, September 2026 for the bays and the 2 October deadline.
- Oxfordshire School Streets, Let’s Talk Oxfordshire for the 2 September start, the ANPR enforcement, the exemptions and the reason for the delay.
- Oxford to Caversham: A4074 corridor, proposed 40mph and 50mph speed limits, Oxfordshire County Council, 9 October 2025 for the decision, the consultation responses and the X40 journey time observations.
- National Highways seven-day road closure report, edition of 29 October to 4 November 2026, for the A404(M) junction 9a and M40 junction 4 closures, the A34 Marcham to Abingdon, Peartree to Hinksey Hill, West Ilsley and Chilton nights, and the absence of any junction 8/9 or Milton to Chilton closure.
- Oxfordshire multiple temporary road and public right of way closures, published 28 October 2026 for the made Hurdlers Green (ref 485) and Mill Road, North Weston (ref 440) orders of 26 October and the Mill Road diversion.
- GWR timetable changes, Saturday 24 to Friday 30 October 2026 for the Sunday 25 October retiming of local stopping services, and GWR timetable changes, Saturday 31 October to Friday 6 November 2026 for the Sunday 1 November Reading to Didcot service and the 0018 Henley-on-Thames to Reading finishing at Twyford from 3 to 5 November.
- Oxfordshire multiple temporary road closures for various works, published 21 October 2026 for the Marsh Baldon order of 19 October, the second Crown Road closure, Fane Drive in Berinsfield, and the made Southern Road and Cuxham orders; and Oxfordshire temporary road closures, published 21 October 2026 for Gidley Way in Horspath.
- Oxfordshire multiple temporary road closures, published 14 October 2026 for Old London Road in Benson, the B4009 at Britwell Salome, Rectory Road at Great Haseley, Crown Road in Wheatley, the made Holton order, Baldon Lane at Marsh Baldon, Oxford Way in Chalgrove and the 40mph A418 order at Thame.
- Environment Agency, River Thames restrictions and closures, rechecked 15 November 2026, for the Benson, Marsh, Hambleden and Temple lock closures, the 1 November Marsh Lock power fault, the Henley Long Distance Sculls arrangements, and the Marsh reach and Shiplake restrictions.
- Oxfordshire County Council, how we maintain our roads for the upcoming resurfacing schemes list and the B4445 finish date.
- Fawley Bottom Lane road closure, Oxfordshire County Council, published 9 October 2026 for the order made on 5 October (ref 358) and its diversion.
- Oxfordshire multiple temporary closures, published 7 October 2026 for Rowland Close and Castle Street in Wallingford and Weston Road in Lewknor.
- Oxfordshire footpath closure and speed limit restriction, published 1 October 2026 for the A4074 Chazey Heath limits and the Nuns Acre footpath.
- A34 Peartree to Marcham lay-by closures, National Highways, published 8 October 2026 (NH/SE/2026/A34/85).
- Henley-on-Thames Footpaths 6 and 8 stopping up order, South Oxfordshire District Council, published 9 October 2026 for the Deanfield Road confirmation.
- Binfield Heath and Henley-on-Thames road closures, Oxfordshire County Council, published 6 November 2026 for the West Street order (ref 519) and Common Lane, Binfield Heath (ref 595).
- Oxfordshire multiple traffic notices, published 4 November 2026 for South Stoke, Marsh Baldon and London Road, Postcombe.
- National Highways seven-day road closure report, edition of 9 to 15 November 2026, for the A404, M40 junction 4, M4 junction 8/9, A404(M) and A34 nights.
- Thame road closure for waste water connection works, Oxfordshire County Council, published 11 November 2026 for Windmill Road, Thame (ref 1188).
- National Highways seven-day road closure report, edition of 13 to 19 November 2026, for the A34 Milton to Chilton, Peartree, Milton, Marcham and Botley nights and the M4 junction 8/9 and A404(M) junction 9b closures.
- GWR planned engineering, rechecked 15 November 2026, for the Sunday 22 November two-track working between Paddington and Reading and the 28 and 29 November Paddington closure, and GWR timetable changes, Saturday 14 to Friday 20 November 2026 for the 0018 Henley-on-Thames to Reading finishing at Twyford from 17 to 19 November.
- Oxfordshire County Council live roadworks map (one.network) for current closures and diversions.
- Oxfordshire County Council planned road maintenance for the resurfacing programme, the 33 sites and the council’s caveat about weather.
- Didcot and area improvements and GRAHAM to build Didcot to Culham river crossing, 3 August 2026 for the four schemes, the funding and the contractor.
- Oxfordshire welcomes return of £2 single bus fare cap, 27 July 2026 for the January 2027 start.
- South Oxfordshire District Council car park pages for every tariff, permit price and space count quoted: Henley-on-Thames, Kings Road, Wallingford, Thame and Didcot, plus the car parks index for the Off-Street Parking Order review.
Roadworks dates move, and an order the council only intends to make can be dropped. Check the linked council pages before you set off. Where the trains go is on Henley trains to London; what is being built and where is on Henley planning. The race itself is on our Henley Half Marathon page.