Campaigners want Oxfordshire's audit committee to investigate the £22.3m Watlington Relief Road. They say £14.1m is committed with no planning permission.

Campaigners have asked Oxfordshire County Council’s Audit and Governance Committee to open an independent investigation into the £22.3 million Watlington Relief Road. Oxfordshire Roads Action Alliance (ORAA) says £14.1 million of the council’s own money has been committed to the road with no way identified of getting it back from developers, no planning permission and no updated business case since 2021.

The committee was due to take up the scheme at its meeting on Wednesday 18 November, from 1pm, under item 20 (work programme) of its published agenda.

Overview

  • What: a referral of the Watlington Relief Road from the council’s Performance and Corporate Services Overview and Scrutiny Committee, which voted on 18 September 2026.
  • Who is asking: Oxfordshire Roads Action Alliance, a campaign group and formal consultee on the road’s planning application.
  • The money, as ORAA gives it: a £22.3m project, £14.1m of it from council funds.
  • What ORAA wants: the referral accepted in full, with the investigation scoped by the council’s Head of Internal Audit and Counter Fraud and its Section 151 (finance) officer, backed by outside legal advice.

Why the scrutiny committee sent it on

The referral came from councillors on the budget scrutiny committee. ORAA says they spent six months asking the council’s Cabinet for a full options appraisal, one that tests the road against the council’s Local Transport and Connectivity Plan, including Policy 36a. That policy, in the plan’s own words, is to “only consider road capacity schemes after all other options have been explored”. ORAA says what the councillors received in June 2026 was “an unpublished, four-paragraph summary” with no supporting evidence attached.

The committee’s decision on 18 September, as the alliance quotes it, was that “the matter be referred to the Audit and Governance Committee, with a request that it consider reviewing the relief road project as a priority and examining whether similar governance, due-process or option-appraisal issues existed in other major capital projects”. ORAA calls the cross-party referral “unprecedented”.

The alliance’s six concerns

ORAA set out its case in a press release on 17 November:

  • £14.1m with no source to replace it. The alliance says that despite public assurances the money committed from council reserves in 2025/26 and 2026/27 would be replaced, it comes from internal capital funding “and has no source to replace the expenditure”.
  • Staff costs charged to capital. The road has been worked on by three teams of external consultants, officers and seconded staff in turn, ORAA says. It points to the external auditor EY’s 2025/26 Audit Results Report (item 6 on the same agenda), which found that “capitalised labour costs were not supported by appropriate evidence” and that “there was no appropriate evidence that timesheets were reviewed and approved prior to capitalisation”.
  • Top risk rating. The council’s strategic risk register (item 10) rates both Major Infrastructure (SR22) and Organisational Capacity at the maximum 25 out of 25, with controls rated only “Partially Effective”.
  • No Cabinet business case since 2021. In September 2021 Cabinet approved £2.893m to complete Stage 2 design and procurement. At that point, ORAA says, the road was costed at £7.13m to £9.98m and paid for by government Growth Deal grants and developer (Section 106) contributions, with no council reserves.
  • School expansion land. The alliance says planning records raise questions about why a 2.3 hectare option on land for a school expansion, already secured under earlier outline consents ahead of the May 2028 expiry of temporary classrooms, was renegotiated onto a site cut off from the school by a 30mph lorry route.
  • Who runs the review. The agenda proposes that “relevant officers” work with the committee’s chair to design it. ORAA says that risks letting the highways, consultancy and legal staff who worked on the scheme “mark their own homework”.

In the release, an ORAA spokesperson said: “External auditors have already noted unapproved staff timesheets being charged to capital budgets, while the Council’s own risk register notes Major Infrastructure sits at a maximum 25 out of 25 risk rating. Budget scrutiny members asked for an options appraisal for six months and were given just four short paragraphs. Tomorrow, the Audit and Governance Committee must stand up for Oxfordshire taxpayers by ordering a genuinely impartial Internal Audit investigation, independent of the officers, external consultants, and legal teams working on the council’s own project.”

How the budget grew

The alliance’s timeline of the scheme sets out how the council money arrived:

  • December 2024: the Cabinet proposed £11.1m extra for the road from a £13.620m fund for market town active travel.
  • February 2025: the 2025/26 budget was approved with that £11.1m added to the road’s budget.
  • February 2026: the 2026/27 budget added £3m to the £11.1m. A Green group amendment to remove the £14.1m failed and was withdrawn, according to ORAA.
  • September 2026: ORAA says a third planning agent is preparing an updated application, with new traffic modelling and flood design, to resubmit in 2027, and that spending could pass £5m during 2026.

The council’s own budget consultation report for 2025/26, which the alliance sent us, drew 143 responses to its feedback form. Roads and transport was the most mentioned theme, with 27 mentions under new investments. The report records “objections to using active travel funds for the Watlington relief road” and quotes one respondent: “The Watlington Relief Road is not an active travel scheme and it should not be grouped with it.”

What it means for you

The road is a county council scheme, so the money committed to it is county council money, raised in part from council tax across Oxfordshire. It does not yet have planning permission. ORAA’s timeline says the council planned two public information events on the designs in November, in Watlington and Pyrton, with details on the council’s Watlington Relief Road project page.

The next chance to comment on the money is the county council’s Let’s Talk consultation on its draft 2027/28 budget. ORAA says the consultation runs for six weeks and has to close by early January, so it expects it to open soon, and that it will be checking whether the road is still listed under market town active travel in the capital budget and what the council says about how it would pay to build it.

Earlier on Watlington: the community buyout of the Watlington Arcade.

Source: Oxfordshire Roads Action Alliance.